MEADOWBROOK RESURFACE

meadowbrook

Contacts

Public Works Director Mr. Paul Hartwig
Em: phartwig@cpwa.us
Ph: (509)-394-8526

Construction on Meadowbrook Boulevard between Lamperti Street and SR 125 will begin on March 22, 2021.  Construction is anticipated to last from late March to mid-May. Work will include ADA sidewalk improvements, spot sidewalk replacements, grinding and overlaying Meadowbrook Boulevard with new pavement.  Business access will be maintained at all times during construction.  To maintain access to at least one driveway on the east side and one driveway on the west side of Meadowbrook Boulevard will be open at a minimum.  Traffic control signing will be installed to help better navigate the construction zone.